Dave Carron
2005-04-21 08:09:03 UTC
I am using the resource usage sheet as a method to create a rolling 6 week
work schedule for a number of resources. The method I am using is a bit
cumbersome and I am wondering if there is an easier way to do it. What I do
each week is as follows:-
1. Go to resource usage view and expand all resource assignments.
2. Make sure the timescale is formatted to show at least 6 weeks.
3. Select columns from the table part (resource, id, work, remaining work,
actual work and several dates [I have modified this table]) and cut and paste
to excel.
4. Select 6 weeks of work columns and cut and paste to excel.
5. Convert the work values from text e.g. "3.5d" to equivalent hours using
formulas in excel. (Can this step be avoided by getting project to output
numbers ?)
6. From a seperate project task view cut and paste the task id and a custom
text field into another worksheet and use vlookup to get the custom text into
my work schedule. (I have not found a way to get a task field to appear in a
work view).
7. Further manipulate the data in excel and use a pivot table to get the
work schedule by resource.
8. Have a lie down in a dark room !
I'm assuming there must be an easier way ? I'm using MS Project 2000 SR-1.
Thanks,
Dave Carron
work schedule for a number of resources. The method I am using is a bit
cumbersome and I am wondering if there is an easier way to do it. What I do
each week is as follows:-
1. Go to resource usage view and expand all resource assignments.
2. Make sure the timescale is formatted to show at least 6 weeks.
3. Select columns from the table part (resource, id, work, remaining work,
actual work and several dates [I have modified this table]) and cut and paste
to excel.
4. Select 6 weeks of work columns and cut and paste to excel.
5. Convert the work values from text e.g. "3.5d" to equivalent hours using
formulas in excel. (Can this step be avoided by getting project to output
numbers ?)
6. From a seperate project task view cut and paste the task id and a custom
text field into another worksheet and use vlookup to get the custom text into
my work schedule. (I have not found a way to get a task field to appear in a
work view).
7. Further manipulate the data in excel and use a pivot table to get the
work schedule by resource.
8. Have a lie down in a dark room !
I'm assuming there must be an easier way ? I'm using MS Project 2000 SR-1.
Thanks,
Dave Carron