Mike
2005-01-18 18:35:32 UTC
Hi all,
I've got a fairly simple problem, but I can't seem to figure out the
answer.
I'm trying to schedule a recurring set of three tasks which each use
different resources. Each task is dependent on the previous and each
must occur immediately after its predecessor has finished. This is the
most important factor. Resource allocation and duration are not as
important.
So I set them up as follows:
Task 1A 2 weeks Driver
Task 2A 6 weeks Guide 1
Task 3A 8 weeks Guide 1
Task 1B 2 weeks Driver
Task 2B 6 weeks Guide 2
Task 3B 8 weeks Guide 2
Task 1C 2 weeks Driver
Task 2C 6 weeks Guide 1
Task 3C 8 weeks Guide 1
(etc.)
Each task 2 has a FS+0d dependency on Task 1. Each task 3 has a FS+0d
dependency on Task 2. Everything is schedule ASAP.
Now, when I apply resource levelling, Project moves things around to
maximize resource usage, as you'd expect. The problem is that I want
it to enforce the zero lag time, while making sure that resources are
not over-allocated (I don't care if they are under-allocated.)
Is there a resource levelling option that will help? Should I be
trying another approach?
Thanks!
- Mike
I've got a fairly simple problem, but I can't seem to figure out the
answer.
I'm trying to schedule a recurring set of three tasks which each use
different resources. Each task is dependent on the previous and each
must occur immediately after its predecessor has finished. This is the
most important factor. Resource allocation and duration are not as
important.
So I set them up as follows:
Task 1A 2 weeks Driver
Task 2A 6 weeks Guide 1
Task 3A 8 weeks Guide 1
Task 1B 2 weeks Driver
Task 2B 6 weeks Guide 2
Task 3B 8 weeks Guide 2
Task 1C 2 weeks Driver
Task 2C 6 weeks Guide 1
Task 3C 8 weeks Guide 1
(etc.)
Each task 2 has a FS+0d dependency on Task 1. Each task 3 has a FS+0d
dependency on Task 2. Everything is schedule ASAP.
Now, when I apply resource levelling, Project moves things around to
maximize resource usage, as you'd expect. The problem is that I want
it to enforce the zero lag time, while making sure that resources are
not over-allocated (I don't care if they are under-allocated.)
Is there a resource levelling option that will help? Should I be
trying another approach?
Thanks!
- Mike