Discussion:
Gnatt Chart and Non Working Days
(too old to reply)
Deb's Project's questions
2005-05-20 21:16:03 UTC
Permalink
I would like to supress the gray non working time on the Gnatt Chart (Sat &
Sun) so that it does not show at all.
--
Deb
JulieS
2005-05-20 21:21:47 UTC
Permalink
Hi Deb,

I assume you wish to show just Monday through Friday in the Gantt Chart and
I'm afraid that is not possible.

Sorry, hope this helps.
Julie


"Deb's Project's questions"
Post by Deb's Project's questions
I would like to supress the gray non working time on the Gnatt Chart (Sat &
Sun) so that it does not show at all.
--
Deb
Murali
2005-05-20 23:52:03 UTC
Permalink
Deb,

You can do that by setting your timescale to weeks instead of days.

Regards,
Murali
Post by JulieS
Hi Deb,
I assume you wish to show just Monday through Friday in the Gantt Chart and
I'm afraid that is not possible.
Sorry, hope this helps.
Julie
"Deb's Project's questions"
Post by Deb's Project's questions
I would like to supress the gray non working time on the Gnatt Chart (Sat &
Sun) so that it does not show at all.
--
Deb
Steve House [Project MVP]
2005-05-22 12:20:01 UTC
Permalink
A week still corresponds to 7 days, not 5.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
Post by Murali
Deb,
You can do that by setting your timescale to weeks instead of days.
Regards,
Murali
Post by JulieS
Hi Deb,
I assume you wish to show just Monday through Friday in the Gantt Chart and
I'm afraid that is not possible.
Sorry, hope this helps.
Julie
"Deb's Project's questions"
Post by Deb's Project's questions
I would like to supress the gray non working time on the Gnatt Chart (Sat &
Sun) so that it does not show at all.
--
Deb