mic994
2005-03-29 13:37:08 UTC
I am running into a problem when trying to save a baseline. Could someone
please explain the best practices for saving a baseline/creating a project
plan. Here are the steps I have done:
1) Created project plan, added tasks, set durations, added dependancies,
assigned resources (all tasks are effort driven and fixed units)
2) Leveled the project - Leveling Order set to standard - none of the
checkboxes selected
3) I then save the baseline
At this point, my start date and finish dates change. My start and finish
dates shouldn't change when I save a baseline. Any idea why the start and
finish dates changing when saving a baseline?
Thanks
please explain the best practices for saving a baseline/creating a project
plan. Here are the steps I have done:
1) Created project plan, added tasks, set durations, added dependancies,
assigned resources (all tasks are effort driven and fixed units)
2) Leveled the project - Leveling Order set to standard - none of the
checkboxes selected
3) I then save the baseline
At this point, my start date and finish dates change. My start and finish
dates shouldn't change when I save a baseline. Any idea why the start and
finish dates changing when saving a baseline?
Thanks