Post by GlennI have a schedule and I have listed Start Dates for each task. The schedule
has changed and therefore my Actual Start Dates have moved. When I place the
new date for the Actual Start field into my schedule, it automatically
changes my Start Date to be the same as the Actual Start.
Why does Project set these dates to be the same?
thanks for any thoughts on this
Glenn,
This exact same question was asked a few days ago in this newsgroup but
I don't remember the date. Try doing a search a couple days back.
Basically the reason lies in Start versus Actual Start versus Baseline
Start. The Start field is the original plan (an estimate). Once a plan
is laid out, a baseline is set to "lock in" the original plan. Then when
the task actually starts, the Start field is updated to reflect reality
(i.e. Actual Start). The Baseline Start field is used to measure
schedule variance.
One thing that caught my eye about your post. The first sentence implies
that you manually entered Start dates for each task. This is a common
mistake for new users. Directly entering Start (or Finish) dates for
tasks will set a constraint on that task and not allow Project to
dynamically calculate the schedule. The Start date of the first task in
the plan is determined by the Project Start Date (Project/Project
Information). Normally, except in a few cases where truly independent
tasks occur, the Start date of all other tasks should be calculated by
Project based on the task Duration and linkages between tasks.
Hope this helps.
John
Project MVP