mikejw
2009-10-20 20:23:01 UTC
Hello,
I have several groupings that have a summary task and 10 milestones (0
duration) underneath. At the moment, 8 of those milestones have been
completed, 2 are incomplete, however, the percent complete on their summary
task is showing 0%. Playing around, I noticed that if I change the duration
from 0 to 1, the corrrect percent complete shows up at the summary level.
Can someone help me understand why the summary task's percent complete is
not being updated as task below it complete?
Thank you,
MikeW
I have several groupings that have a summary task and 10 milestones (0
duration) underneath. At the moment, 8 of those milestones have been
completed, 2 are incomplete, however, the percent complete on their summary
task is showing 0%. Playing around, I noticed that if I change the duration
from 0 to 1, the corrrect percent complete shows up at the summary level.
Can someone help me understand why the summary task's percent complete is
not being updated as task below it complete?
Thank you,
MikeW