If that's the case and you do have to manage each phase of a drawing
separately, each drawing becomes a summary task with the three phases as
subtasks within them. Link the subtasks FS (finish-to-start) and add
appropriate lag times in the links to account for the time waiting for the
approvals to come back. Don't set start and end dates for the individual
sub tasks, estimate their durations and let Project calculate all their
dates. The durations you supply on the task Entry table in the Gantt chart
are the estimated, or scheduled, durations. Once you get them all in, save
a baseline so you'll have a record of where things start out. Then, as you
artists report the actual time it took to do each task and the dates they
actually did them, switch to the Tracking table and enter them as Actual
Start and Actual Finish or Actual Duration. When you go back the entry
table you'll find the duration, start, and finish of completed tasks will
have been updated to reflect the actuals and downline task's scheduled dates
will have been recalculated. Nore that you can NOT update the dates and
durations in the Entry table by hand to enter the actuals - you must switch
to a table that shows the fields specifically named Actual Start, Actual
Finish, Actual Duration and Remaining Duration (NOT Start, Finish, and
Duration) to update the schedule with what actually took place.
HTH
--
Steve House
MS Project Trainer & Consultant
Post by AllyYou guys are seriously helpful!
I'm still having a lot of trouble trying to get my head around things though.
Steve, as much as what you said would simplify everything for me amazingly,
the artists do actually have set deadlines to have their three thumbnails in
for approval, then another deadline for their detail sketches, etc.
Is there any way I can make this time still flexible though? If I didn't set
a baseline, or allocated days, (for example) would just entering their hours
be enough to make the start/finish dates move the way I want?
Post by Steve HouseMight I suggest .... It's not the job of the project manager to micromanage
the resource's workday. Since the same resource is doing the concept, the
sketch, and the final art, you don't have multiple resources to coordinate
in the production of a single picture. From your description it doesn't
sound like they have to split up their work to make room for other
resource's activities - ie, submit the concept for approval from another
party before starting the sketch - so just estimate the total time from the
start of the process until the delivery the final picture and be done with
it. Managing the phases just to be in control is pointless. The fact you
CAN track his hours on each component of the work doesn't mean that you
OUGHT to do it or that it makes sense to do it. Now if you have a number of
resources involved in the production of a single picture and you need to
coordinate their activities, that's a different story. But if just one
resource is responsible for the entire process. he's perfectly capable of
managing his workflow all on his own - let him do his job the way he knows
is best to do it. All a PM needs to be concerned with is when he starts and
when he delivers the completed picture. What happens in the middle just
doesn't matter.
--
Steve House
MS Project Trainer & Consultant
Post by AllyHm.
I'm just wondering if I should start over again and what the best way to
implement it would be.
I'm working with artists who are assigned three tasks at once, and each task
(a single picture) is split into different sections - for example a concept,
a detail sketch, and then the finished piece of art. They have
durations
set
for each to be completed (and the sketch has to follow the concept, the
finished art to follow the sketch, and in the set of three they do all the
concepts at once, then once approved, all the sketches, etc) but they can
complete things ahead of or behind time, shown in actual duration.
What we want to do is add in their daily hours (actual work) and have
it
be
the precedent that the proceeding start and finish dates are based
upon,
but
any empty tasks in the future still set to have the preset durations so we
can tell when they're likely to finish.