MS Project: Listing Resource Names by Task Bars
(too old to reply)
John Lucero Criswell
2005-05-05 16:24:05 UTC
Permalink
Hi,

For some reason, on my most recent project MS Project is not listing the
resource names by the Task Bars.

I am want to print a Gantt Chart showing who is doing what. I have gone into
Bar Styles, Text Tab and indicated Resource Names, Initials and so forth be
listed to the left, right, above... of the the task bars (I have made a few
tries).

Is there a setting I may have accidentally changed with errant key strokes
to cause this problem? Listing resources by task bars has been successful (It
is a default setting!) in my other projects.

Thanks in advance for your advice. - John
--
John Lucero Criswell
Campaign Director
Community Shares of Greater Cincinnati
JulieS
2005-05-05 17:15:42 UTC
Permalink
Hi John,

If you had formatted individual bars through the Format>Bar command it
over-rides any format set through Format Bar Styles. Select all tasks in
the project, choose Format>Bar and click the Reset button to remove any
individual formatting.

Hope this helps. Let us know how you get along.

Julie
Post by John Lucero Criswell
Hi,
For some reason, on my most recent project MS Project is not listing the
resource names by the Task Bars.
I am want to print a Gantt Chart showing who is doing what. I have gone into
Bar Styles, Text Tab and indicated Resource Names, Initials and so forth be
listed to the left, right, above... of the the task bars (I have made a few
tries).
Is there a setting I may have accidentally changed with errant key strokes
to cause this problem? Listing resources by task bars has been successful (It
is a default setting!) in my other projects.
Thanks in advance for your advice. - John
--
John Lucero Criswell
Campaign Director
Community Shares of Greater Cincinnati
John Lucero Criswell
2005-05-05 18:34:01 UTC
Permalink
Julie,

That worked beautifully! Thank you for taking the time. - John
--
John Lucero Criswell
Campaign Director
Community Shares of Greater Cincinnati
Post by JulieS
Hi John,
If you had formatted individual bars through the Format>Bar command it
over-rides any format set through Format Bar Styles. Select all tasks in
the project, choose Format>Bar and click the Reset button to remove any
individual formatting.
Hope this helps. Let us know how you get along.
Julie
Post by John Lucero Criswell
Hi,
For some reason, on my most recent project MS Project is not listing the
resource names by the Task Bars.
I am want to print a Gantt Chart showing who is doing what. I have gone into
Bar Styles, Text Tab and indicated Resource Names, Initials and so forth be
listed to the left, right, above... of the the task bars (I have made a few
tries).
Is there a setting I may have accidentally changed with errant key strokes
to cause this problem? Listing resources by task bars has been successful (It
is a default setting!) in my other projects.
Thanks in advance for your advice. - John
--
John Lucero Criswell
Campaign Director
Community Shares of Greater Cincinnati
JulieS
2005-05-05 18:40:19 UTC
Permalink
Hi John,

You are very welcome and thanks for the feedback. Let us know if we can
assist again in the future.

Julie
Post by John Lucero Criswell
Julie,
That worked beautifully! Thank you for taking the time. - John
--
John Lucero Criswell
Campaign Director
Community Shares of Greater Cincinnati