Robin
2009-10-05 17:36:11 UTC
I am working in an EPM environment where the Resource was initially selected
from our ERP and assigned to tasks within a project schedule. I have
removed the Resource Assignment from all tasks in the project schedule and
have saved the project schedule. When I then attempt to delete the Resource
from the Resource Sheet, I get a series of warning messages. The first is
'Resource must be removed from task assignments before it can be deleted'.
The next message, which can appear a number of times is, 'An error has
occurred, contact your System Administrator and let them know which project
the error has occurred in'. I’m thinking that these messages are occurring
because the Resource is assigned to other projects. It seems that I get the
second message as many times as the number of other projects that the
resource is assigned to – visible via the Resource Usage view. (Eventually
the messages stop and the Resource is deleted) Also supporting my thinking
is the fact that testing this scenario with a Resource that has no other
assignments other than the one I deleted him from, does not invoke these
error messages. Is this the case? If so, what is actually happening
‘behind the scenes’ in Microsoft Project to invoke these error messages?
Thank you.
from our ERP and assigned to tasks within a project schedule. I have
removed the Resource Assignment from all tasks in the project schedule and
have saved the project schedule. When I then attempt to delete the Resource
from the Resource Sheet, I get a series of warning messages. The first is
'Resource must be removed from task assignments before it can be deleted'.
The next message, which can appear a number of times is, 'An error has
occurred, contact your System Administrator and let them know which project
the error has occurred in'. I’m thinking that these messages are occurring
because the Resource is assigned to other projects. It seems that I get the
second message as many times as the number of other projects that the
resource is assigned to – visible via the Resource Usage view. (Eventually
the messages stop and the Resource is deleted) Also supporting my thinking
is the fact that testing this scenario with a Resource that has no other
assignments other than the one I deleted him from, does not invoke these
error messages. Is this the case? If so, what is actually happening
‘behind the scenes’ in Microsoft Project to invoke these error messages?
Thank you.