Discussion:
Printing to Adobe PDF in MS Project
(too old to reply)
MarkW
2008-10-14 14:04:01 UTC
Permalink
I have a user who is attempting to use the Adobe PDF printer driver from
within MS Project but no matter which file you try, whether it is large or
small, Project hangs during the conversion process. I have on occasion also
received a message 'Printer connection isn't working. Check your printer
connections and try again'.

I’ve tried changing the printer port for Adobe, thinking it may have
something to do with it attempting to print after saving, but that made no
difference. Every other program appears to work ok when printing on the
associated PC.

Does anybody have any alternative suggestions that I can try to resolve this
problem?

Thanks in advance.
JulieS
2008-10-14 14:07:04 UTC
Permalink
Hi mark,

Are you using Project 2007? There have been reports that turning
off the 3D Gantt Bar display helps. See Tools> Options, view tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Post by MarkW
I have a user who is attempting to use the Adobe PDF printer driver from
within MS Project but no matter which file you try, whether it is large or
small, Project hangs during the conversion process. I have on
occasion also
received a message 'Printer connection isn't working. Check your printer
connections and try again'.
I've tried changing the printer port for Adobe, thinking it may
have
something to do with it attempting to print after saving, but that made no
difference. Every other program appears to work ok when printing on the
associated PC.
Does anybody have any alternative suggestions that I can try to resolve this
problem?
Thanks in advance.
MarkW
2008-10-14 14:23:02 UTC
Permalink
Hi Julie

Thanks for the response. Yes it is Project 2007 that is being used. I will
go and try your suggestion on the PC having the problem and get back to you.

Cheers
Mark
Post by JulieS
Hi mark,
Are you using Project 2007? There have been reports that turning
off the 3D Gantt Bar display helps. See Tools> Options, view tab.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Post by MarkW
I have a user who is attempting to use the Adobe PDF printer driver from
within MS Project but no matter which file you try, whether it is large or
small, Project hangs during the conversion process. I have on occasion also
received a message 'Printer connection isn't working. Check your printer
connections and try again'.
I've tried changing the printer port for Adobe, thinking it may
have
something to do with it attempting to print after saving, but that made no
difference. Every other program appears to work ok when printing on the
associated PC.
Does anybody have any alternative suggestions that I can try to resolve this
problem?
Thanks in advance.
MarkW
2008-10-14 15:52:01 UTC
Permalink
Hi Julie

Looks like your suggestion worked which is great, thanks for all your help
with this.

Mark
Post by JulieS
Hi mark,
Are you using Project 2007? There have been reports that turning
off the 3D Gantt Bar display helps. See Tools> Options, view tab.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Post by MarkW
I have a user who is attempting to use the Adobe PDF printer driver from
within MS Project but no matter which file you try, whether it is large or
small, Project hangs during the conversion process. I have on occasion also
received a message 'Printer connection isn't working. Check your printer
connections and try again'.
I've tried changing the printer port for Adobe, thinking it may
have
something to do with it attempting to print after saving, but that made no
difference. Every other program appears to work ok when printing on the
associated PC.
Does anybody have any alternative suggestions that I can try to resolve this
problem?
Thanks in advance.
JulieS
2008-10-14 17:16:10 UTC
Permalink
You're welcome Mark. Glad to have helped and thanks for the
feedback that turning off the 3D bars worked for you.

Julie
Post by MarkW
Hi Julie
Looks like your suggestion worked which is great, thanks for all your help
with this.
Mark
Post by JulieS
Hi mark,
Are you using Project 2007? There have been reports that turning
off the 3D Gantt Bar display helps. See Tools> Options, view
tab.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Post by MarkW
I have a user who is attempting to use the Adobe PDF printer
driver
from
within MS Project but no matter which file you try, whether it
is
large or
small, Project hangs during the conversion process. I have on occasion also
received a message 'Printer connection isn't working. Check
your
printer
connections and try again'.
I've tried changing the printer port for Adobe, thinking it may
have
something to do with it attempting to print after saving, but
that
made no
difference. Every other program appears to work ok when
printing
on the
associated PC.
Does anybody have any alternative suggestions that I can try to resolve this
problem?
Thanks in advance.