josh.butcher
2006-03-16 23:22:27 UTC
Question: Is there a way to have all tasks that use the one calendar be
hidden behind the non-working time bars while tasks that use another calendar
are shown in front of them?
Background:
I'm using multiple calendars in MS Project 2003, one for regular working
hours and one for overtime working hours. The regular calendar is a
standard, 8-5, 40 hour work week with the company's holiday information
included. The overtime calendar is contains only 8 hour (8-5) days
throughout.
Management prefers that the non-working time in the Gantt chart view cover
(hide) task bars that cross over between weeks. For example, if a task is
using the standard calendar and needs to over lap two weeks, the part of the
task bar that overlays the weekend needs to be hidden by the non-working time
bar (since weekends aren't part of the standard calendar).
The regular calendar is set as the Project's default (standard) calendar.
The thought was that if overtime would be needed to complete a task on time,
then this could be shown by switching the task in question to the overtime
calendar. Then the Gantt chart would visually reflect which tasks had needed
overtime work to be completed on time.
Verbose question:
The problem is that all tasks are overlapped by the non-working time bars,
regardless of which calendar the task is assigned to. Overtime tasks as well
as regular calendar tasks are hidden behind non-working time grey bars.
I'm wondering if there is a way to have all tasks that use the standard
calendar be hidden behind the non-working time bars while those tasks that
use the overtime calendar are shown in front of them. Thanks.
hidden behind the non-working time bars while tasks that use another calendar
are shown in front of them?
Background:
I'm using multiple calendars in MS Project 2003, one for regular working
hours and one for overtime working hours. The regular calendar is a
standard, 8-5, 40 hour work week with the company's holiday information
included. The overtime calendar is contains only 8 hour (8-5) days
throughout.
Management prefers that the non-working time in the Gantt chart view cover
(hide) task bars that cross over between weeks. For example, if a task is
using the standard calendar and needs to over lap two weeks, the part of the
task bar that overlays the weekend needs to be hidden by the non-working time
bar (since weekends aren't part of the standard calendar).
The regular calendar is set as the Project's default (standard) calendar.
The thought was that if overtime would be needed to complete a task on time,
then this could be shown by switching the task in question to the overtime
calendar. Then the Gantt chart would visually reflect which tasks had needed
overtime work to be completed on time.
Verbose question:
The problem is that all tasks are overlapped by the non-working time bars,
regardless of which calendar the task is assigned to. Overtime tasks as well
as regular calendar tasks are hidden behind non-working time grey bars.
I'm wondering if there is a way to have all tasks that use the standard
calendar be hidden behind the non-working time bars while those tasks that
use the overtime calendar are shown in front of them. Thanks.